ABOUT THE SERVICE:
An occupancy permit is being issued to the applicant before any building / structure is used or occupied. This permit shall be secured after the completion of a structure. If
there is any change in the existing use or occupancy classification of a building. Structure or any portion thereof, occupancy permit is also required.
REQUIREMENTS:
HOW TO AVAIL OF THE SERVICE
FOLLOW THESE STEPS | IT WILL TAKE YOU | PLEASE APPROACH |
1. Secure certificate of completion forms and completion forms from any member of the building staff. | 5 minutes | Edgar T. Hermogeno
Draftsman II |
2. Second endorsement present duly accomplished forms and related documents to any member of the building staff for initial verification of the requirements. A 2nd endorsement will be given to the client for the issuance of a Fire Safety Inspection Certificate from the Bureau of Fire Protection. | ½ day | BFP Personnel |
3. Submit requirements after clearance has been secured from BFP together with the duly accomplished forms and related documents; safety certificates as built-plans; and detailed sketch of location. Request for an inspection schedule. | 15 minutes | Edgar T. Hermogeno
Draftsman II |
4. Review / Evaluation | 30 minutes | Edgar T. Hermogeno
Draftsman II |
5. Building Inspection.
Building inspector/ technical staffs conduct actual inspection of the completed building / structure and checks. If the same is in accordance with the approved plans and specifications. |
1 day | Edgar T. Hermogeno
Draftsman II |
6. Preparations of Inspection Report (Optional)
If the building inspector finds that the completed project has deviations from the approved plans, you will be given an inspection report. That lists the needed corrections or other documents required. |
30 minutes | Edgar T. Hermogeno
Draftsman II |
7. Issuance of order of payment
EIC prepares an order of payment indicating an assessment of fees to be paid. |
15 minutes | Edgar T. Hermogeno
Draftsman II |
8. Payment of Fees
Proceed to the MTO and pay the required fees. |
10 minutes | Ma. Teresa H. Betito
ICO- Municipal Treasurer |
9. Present official receipt | 1 minute | |
10. Processing of occupancy permit | 15 minutes | Edgar T. Hermogeno
Draftsman II |
11. Issuance of occupancy permit is duly approved by the building official. | 10 minutes | Berlin H. Dimaculangan
Municipal Engineer |